Question: Where is my project base point in Revit?

How do I find the base point of a project in Revit?

Display Coordinate Origin Points

  1. Open the desired view.
  2. Click View tab Graphics panel (Visibility/Graphics).
  3. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site, and expand it.
  4. To display the project base point, select Project Base Point.
  5. To display the survey point, select Survey Point.

How do you set a project base point in Revit?

Define the Project Base Point

  1. Open the site plan view or another view that displays it. …
  2. To select the project base point, move the cursor over the symbol and look at the tooltip or the status bar. …
  3. Drag the project base point to the desired location.

How do you set a project base point and survey point in Revit?

To make these points visible:

  1. Click View tab > Graphics panel > Visibility/Graphics.
  2. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site. …
  3. To display the project base point, select Project Base Point.
  4. To display the survey point, select Survey Point.
IMPORTANT:  How do you unhide a feature tree in Solidworks?

What is Project Base Point?

The project base point can be used to establish a reference for measuring distances and positioning objects in relation to the model. Initially, in stock templates, it identifies the origin (0,0,0) of the project coordinate system. Use the project base point as a reference point for measurements across the site.

How do you hide a project base point in Revit?

To temporarily display the project base point and the survey point in a view, on the View Control Bar click (Reveal Hidden Elements).

How do you change project level in Revit?

Manage tab> Project Location> Coordinates> Specify Coordinates at Point:

  1. Select the ground level line and specify elevation:
  2. Ground level still says 0. Select the ground level line and change the type to Shared Datum:
  3. Ground level now shows the Shared Datum levels:

How do I set shared coordinates in Revit?

To do so, follow the instructions below or watch our short video.

  1. Open the model for which you want to bring the proper coordinates into.
  2. Turn on the visibility of the site points. …
  3. Create a new shared site and rename it. …
  4. Link in the model with the proper shared site reference. …
  5. Relocate your model.

What is a survey point?

The survey point represents a known point in the physical world, such as a geodetic survey marker. The survey point is used to correctly orient the building geometry in another coordinate system, such as the coordinate system used in a civil engineering application.

How do you reset Coordinates in Revit?

Reset Shared Coordinates

  1. Open the host model whose coordinates you want to reset.
  2. Click Manage tab Project Location panel Coordinates drop-down (Reset Shared Coordinates).
  3. Click to close the message indicating the shared coordinates have been reset.
IMPORTANT:  How do I download AutoCAD Civil 3D student?

How do I find Coordinates in Revit 2020?

Acquire Coordinates

  1. Open the host model.
  2. Link the file from which you want to acquire coordinates. The link can be topography, a DWG or DWF file, or a Revit model.
  3. Click Manage tab Project Location panel Coordinates drop-down (Acquire Coordinates).
  4. Place the cursor on a link, and click.

What is acquire Coordinates in Revit?

Acquire Coordinates. When you acquire coordinates from a linked Revit project, the shared coordinates of the linked project become the shared coordinates of the host project, based on the position of the linked project instance in the host project. There is no change to the host project’s internal coordinates.

How do you specify Coordinates?

Relative Coordinates. To specify absolute Cartesian coordinates: Enter a command requiring coordinates, for example Line. Specify the X, Y- and Z-coordinates separated by commas, for example 0,0,0.